July 2021

Location: Winnipeg, Manitoba

Project Goal:

Our goal is to provide safe demolition services to the client looking to improve building tenancy conditions.

Scope:

We provided interior demolition and subcontract slab cutting.

Number of Crew Involved with the Project:

6 total people on site. In addition  the project involved drivers to pick up, empty, and replace the bins, as well as  the safety supervisor.

Duration:

2 – 3 weeks to complete.